Question 1:

A technician needs to replace a server component with orange tabs/releases. Which set of paired steps should the technician take to complete this task?

A. Power off the server Apply anti-static procedures

B. Remove power cables Cold swap the component

C. Cold swap the component Apply anti-static procedures

D. Hot swap the component Apply anti-static procedures

Correct Answer: D

Reference https://www.sos.state.co.us/pubs/elections/VotingSystems/DVS-DemocracySuite/documentation/Dell_Poweredge_R630_Owner_Manual.pdf (84)


Question 2:

A technician creates two virtual disks and assigns a dedicated hot spare to each virtual disk. They also create a global hot spare. A drive fails on the second virtual disk. What is the result?

A. Dedicated hot spare for the virtual disk replaces the failed drive.

B. Global hot spare replaces the failed drive.

C. Copyback operation occurs between the failed drive and the dedicated hot spare.

D. Copyback operation occurs between the failed drive and the global hot spare.

Correct Answer: B

Refe https://www.dell.com/support/article/pk/en/pkbsd1/sln305775/dell-poweredge-how-to-assign-a-hard-drive-in-global-hot-spare-?lang=en


Question 3:

A technician is creating a virtual disk in the DRAC (2x 4 TB NL-SAS in RAID 1) to install Windows 2016. They manually boot to the OS installation media without using the Lifecycle Controller OS Deployment wizard. Only the first 2048 GB on the virtual disk can be partitioned. How should the technician obtain access to the remaining 2 TB (approximately) of storage?

A. Delete the 4 TB virtual disk and create a virtual (boot) disk no longer than 2048 GB.

B. Upgrade to a newer version of the operating system.

C. Use the lifecycle Controller\’s OS Deployment Wizard to deploy the OS on this server.

D. Use F2 to go into the BIOS, change the BIOS boot mode to UEFI, and try again.

Correct Answer: C


Question 4:

Before deploying a server, a customer needs a technician to configure the front panel LCD to display a custom message that contains the customer\’s help desk phone number. However, the server cannot be rebooted. Where can the technician configure the LCD?

A. Lifecycle Controller

B. iDRAC web GUI

C. System BIOS

D. iSM

Correct Answer: C


Question 5:

A technician needs to add a device to SupportAssist Enterprise. Policy requires that no additional software be installed on the server OS. In addition to Username and Password, what information is required to add the device?

A. IP address or hostname for the server OS

B. IP address for Dell TechDirect

C. IP address fir OpenManage Server Administrator

D. IP address or hostname for the iDRAC

Correct Answer: D


Question 6:

Eight new servers have arrived at a datacenter. All use static IP addresses for iDRAC. The technician needs to enable these servers to contact the DHCP server on the network to obtain new IP addresses. What method can the technician use to quickly switch to DHCP?

A. Reboot each server to enable DHCP default settings

B. Boot into CTRL S and change iDRAC settings to DHCP

C. Use the LCD panel to input a new IP address

D. Log in to the iDRAC and enable DHCP

Correct Answer: D

Reference https://www.dell.com/support/article/pk/en/pkbsd1/sln306877/dell-poweredge-how-to-configure-the-idrac-9-and-the-lifecycle-controller?lang=en


Question 7:

A technician is setting up a previously used server. Upon power up, the PERC alerts them to the presence of a foreign configuration. In the iDRAC storage section, the technician checks Foreign View. The foreign array configuration is the same as the configuration needed for the new project. What is a recommended way to prepare the disks for the new project?

A. Edit the foreign configuration and set it to Ready

B. Import the foreign configuration and perform a full initialization

C. Format the foreign configuration and clear the controller configuration

D. Access the Ctrl R utility, clear the foreign configuration and set up array as needed

Correct Answer: D

Reference https://www.dell.com/community/PowerEdge-HDD-SCSI-RAID/PERC-H310-active-drives-are-listed-in-foreign-config/td-p/6126153


Question 8:

A system administrator needs to install OpenManage Server Administrator on 200 servers. What is the quickest way to meet this requirement?

A. Use the Lifecycle Controller to install OpenManage Server Administrator on each server.

B. Install OME and push OpenManage Server Administrator to all 200 servers.

C. Use Microsoft utilities to automate the deployment of OpenManage Server Administrator.

D. Download OpenManage Server Administrator from Dell.com and install on each server.

Correct Answer: D

Reference https://www.dell.com/support/home/pk/en/pkbsd1/drivers/driversdetails?driverid=r89613


Question 9:

A technician replaces a faulty system board on a server. In addition to powering on the system, what step must the technician take to install the correct service tag?

A. Type asset to change the asset tag

B. Login in to the iDRAC

C. Press F11 to start the Boot Manager

D. When prompted by Easy Restore, press Y to restore the Service Tag, license, and diagnostics information

Correct Answer: D

Reference https://cc.cnetcontent.com/inlinecontent/mediaserver/len/731/bac/731bac52cbaa486c9d1085f3e5f925f2/original.pdf


Question 10:

A new Dell customer is ordering servers that have very specific firmware dependencies. Any replaced parts of the same type must match the replaced original part identically. The procedure must be as simple as possible with minimal risk. What action should a technician take to accomplish this goal?

A. Enable the Match Firmware of Replaced Part setting in the system BIOS

B. Install and configure a repository manager

C. Configure servers to access the remote firmware repository

D. Enable the Collect System Inventory On Restart (CSIOR) attribute

Correct Answer: D


Question 11:

A technician needs to update the iDRAC license on a PowerEdge R740 server from Express to Enterprise. The server has the following components:

2x CPUs 384 GB RAM 6x 1 TB drives 1x PSU

The server is powered down but connected to active AC. The user wants it to stay powered down and not connect to any networks. No errors are presently displayed.

How can the technician upgrade the license?

A. The license cannot be upgraded because the user will not allow the server to be powered on

B. The license cannot be upgraded on a single PSU system

C. Power on the server then connect to the iDRAC and upgrade iDRAC license before powering the server down

D. Connect to the iDRAC GUI and upgrade the iDRAC license while the server is powered down.

Correct Answer: C


Question 12:

A user has a server with only one processor installed with 6x 32 GB RDIMMs. A technician was asked to install a second processor. After installing the second processor, the technician finds that the second processor is not operational. What should be done to make the second processor operational?

A. The second CPU socket needs to be enabled

B. Logical processing must be enabled in the BIOS

C. The iDRAC license needs to be at either Express or Enterprise levels

D. The RDIMMs need to be moved so that there are three RDIMMs on each CPU

Correct Answer: D


Question 13:

A server is being up as a VMware ESXi host. A technician needs to install the OS on an internal SD card. They install the SD card. However, during OS installation, the SD card is not visible. What should the technician do to fix the issue?

A. Enable the SD card in the BIOS Settings

B. Format the SD card with an EXT3 partition before installation

C. Move the SD card from slot 2 to slot 1

D. Use Lifecycle Controller to install the SD card

Correct Answer: A

Reference https://www.google.com/url?sa=tandrct=jandq=andesrc=sandsource=webandcd=16andcad=rjaanduact=8andved=2ahUKEwjj2eCyj6HeAhWyxYUKHW4sBJYQFjAPegQIAhACandurl=https://www.sos.state.co.us/pubs/elections% 2FVotingSystems/DVS-DemocracySuite/documentation% 2FDell_Poweredge_R630_Owner_Manual.pdfandusg=AOvVaw2slkf77AG7CKsMUwdpiwVa


Question 14:

A technician is ready to deploy a server. If a critical part such as the system board fails, they must be able to replace the system board, reconfigure components, and update the firmware revisions in the fastest possible time. How should the technician meet this requirement?

A. Back up the profile using the System Profile Settings

B. Use the iDRAC Rollback feature to restore the firmware revisions

C. Use the iDRAC GUI to back up the Server Profile

D. Back up component configurations using iSM

Correct Answer: A


Question 15:

A PowerEdge R640 server has a failure on one of its onboard NICs and sends an alert to technician support. The assigned technician needs to order a FRU to resolve the issue. What action should the technician take?

A. Replace the system board after first backing up the server profile

B. Order a new NDC and replace the failing NDC

C. Use the iDRAC to reset the NDC to default values then reconfigure. If that fails replace the NDC

D. Order a new NIC port then replace the failing NIC port on the NDC

Correct Answer: D